Kerala Seeks Fresh Review Of Mullaperiyar Dam's Safety By Independent Panel Of Experts; Supreme Court Hearing Tomorrow

Mehal Jain

22 March 2022 6:30 PM IST

  • Kerala Seeks Fresh Review Of Mullaperiyar Dams Safety By Independent Panel Of Experts; Supreme Court Hearing Tomorrow

    In the latest affidavit filed before the Supreme Court in the Mullaperiyar dam case, the State of Kerala has sought a fresh review of the safety of Mullaperiyar by Independent panel of experts.Following suggestions have been put forth by the state of Kerala:a. A fresh review of the safety of Mullaperiyar by Independent panel of experts comprising qualified Engineers and experts in the...

    In the latest affidavit filed before the Supreme Court in the Mullaperiyar dam case, the State of Kerala has sought a fresh review of the safety of Mullaperiyar by Independent panel of experts.

    Following suggestions have been put forth by the state of Kerala:
    a. A fresh review of the safety of Mullaperiyar by Independent panel of experts comprising qualified Engineers and experts in the respective fields i.e. design, geology, hydrology, hydro- Mechanical dam safety, construction and supervision, instrumentation, seismicity should be conducted. CWC should consider including international experts also
    b. Comprehensive Dam safety Review Procedures should be carried out in accordance with the Guidelines for Safety Inspection of Dams, January 2018
    c. The terms of reference of the study and details of the agencies for conducting the tests should be shared to the party States and approved by the Supervisory Committee
    d. All tests and investigations should be conducted to check The hydrological, systematic and structural safety of the dam. The committee should ensure that this exercise is carried out with the participation of the officers of Kerala.
    e. The test reports and their findings should be finalised by the supervisory committee and also shared with the state of Kerala. It should be ensured that the study is completed within a definite time-frame.
    The development has happened in a batch of writ petitions filed by Kerala-based petitioners seeking measures to safeguard the 126-year old dam. A Supreme Court ben led by Justice AM Khanwilkar will start final hearing in the matter tomorrow.

    Kerala's affidavit was in reply to the response filed by the State of Tamil Nadu on February 3 to the status report by the Central Water Commission on January 25.

    In January, the Central Water Commission has told the Supreme Court that a "fresh review of the safety of the Mullaperiyar dam is due and is required to be undertaken". The report further stated that the Supervisory Committee constitued by the Supreme Court has recorded in its meetings that the "overall condition of the dam and its appurtenant structure, based upon visual inspection, is satisfactory".
    It is pertinent to note that Kerala and Tamil Nadu have taken contrary stands regarding the safety of the dam. The Kerala Government has stated that the 126-year old gravity dam constructed using lime and surkhi is extremely vulnerable and its destruction can wreak widespread havoc downstream in Kerala. "Logical next step is construction of a new dam to ensure water to Tamil Nadu and security to people living downstream and to decommission the existing dam", Kerala's affidavit filed on October 28 had stated. In a subsequently filed affidavit, the Kerala Government stated that repeated rejuvenation cannot perpetuate the 126-year old dam, and disputed the rule curve adopted by Tamil Nadu to fix the appropriate water level in the reservoir during the heavy monsoon season.
    The state of Tamil Nadu has filed a reply affidavit in the Supreme Court opposing the assertions made by the state of Kerala for the decommissioning of the existing dam and for reconstructing a new dam in that place. Tamil Nadu has said that such repeated assertions by the Kerala Government and the writ petitioners (few individuals and organisations from Kerala) are "wholly impermissible" in view of the 2014 judgment of the Supreme Court on the safety of the dam. The Tamil Nadu Government asserts in its counter-affidavit that the dam has been found to be "hydrologically, structurally and seismically safe"."The repeated assertion of Kerala and Petitioners from Kerala in Writ Petitions filed from time to time inter-alia seek decommissioning of the existing dam and construction of a new dam, which is wholly impermissible in the light of judgment of this Hon'ble Court on the safety of the dam. The dam has been found to be hydrologically, structurally and seismically safe", the affidavit of Tamil Nadu read.
    In the latest affidavit, the State of Kerala sought the reconsideration of the Rule Curve formulated by Tamil Nadu, Comprehensive Instrumentation Plan including seismic instrumentation and other aspects mentioned in the Status Report. The State of Kerala sought the above changes on account of the erratic and heavy rainfall experienced by the State of Kerala during the last 4 years. It is submitted that the State of Tamil Nadu has not addressed the concerns of Kerala raised in the reply affidavit.
    It is submitted that the alleged delay in issuing necessary clearances to various works proposed by Tamil Nadu is in fact due to the delay from the part of Tamil Nadu in submitting the details in proper format or delay in submission of required details.
    It is submitted that the necessary clearances for cutting the trees and the repair work of the approach road from Valakkadavu- Mullaperiyar road has to be sought under the Wild Life (Protection) Act, Forest Conservation Act and Environmental (Protection) Act.
    "Being a Tiger reserve, the state of Kerala has to observe the statutory provisions in letter and spirit and the ecological preservation is a serious issue in the public concern of the state. The question of granting statutory clearances for the above activities under the Wild Life (Protection) Act, Forest Conservation Act and notification under Environmental (Protection) Act does not come under the purview of the Supervisory Committee. The Supervisory Committee is not competent to provide clearances to the above proposals. It is not admitted that repair work of approach road and tree cutting are required to be carried out. Without prejudice to the aforesaid, the time consumed in deciding on the proposals is solely due to the shortcomings in the proposals submitted by the User Agency (Executive Engineer, Periyar Dam Special Division, Cumbum, Theni District, Tamil Nadu). It is submitted that, moreover Tamil Nadu had filed an IA 28/2017 in O.S 3/2006 in 01.03.2017 before the Hon'ble Supreme Court for directions to allow them to carry out repair work of the approach road, cutting of trees through the Forest area located in the State of Kerala for carrying out the balance strengthening measures of the Baby Dam, which is pending before the Hon'ble Supreme Court. The said matters are, therefore, yet to be decided by this Hon'ble Court", it is urged.
    It is stated by Kerala that said rain gauge station has been constructed by the state of Tamil Nadu on land, which is not a part of the land covered by the lease Deed of 1886- "As pointed out in the counter affidavit filed by Kerala to the IA 28/2017 in O.S 3/2006 in 01.03.2017 before the Hon'ble Supreme Court, the state of Kerala has not barred access to the said rain gauge station but only regulated it by insisting on plying through the boat maintained by the Forest Department of Kerala. In the 9th meeting of the Supervisory Committee held on 07.07.2016 the officials of Kerala informed about their decision to establish an inflow forecasting system in the catchment of Mullaperiyar dam. The Installation work has been completed at all 13 stations. But at present there are issues with retrieving the complete set of data for 24 hours from all the stations due to dense forest cover, wildlife and accessibility problems. The format of data from the instruments has been communicated to the Chairman, Cauvery Technical Cell, Tamil Nadu as per their request for generating the File Transfer protocol in Tamil Nadu Cloud server for sharing the rainfall data of Mullaperiyar. The non-validated raw data recorded in the 11 Automatic Rain Gauges and 2 Automatic Weather Stations available from Jan 2020 till Nov 2021, is shared to Tamil Nadu as per their request. Copy of letter is attached as Annexure R2/1 (Page No. 43 ). Once the rectification of the instruments as well as the validation process is completed, data can be shared with Tamil Nadu on real-time basis. Therefore, with this state-of-the-art rainfall network, which will provide real time data, the demand of Tamil Nadu for access to Mullaikodi rainfall gauging station to collect rainfall data does not survive."
    "The Mullaperiyar dam with faces in uncoursed rubble masonry in lime mortar and core in lime surkhi concrete is passing through its 126 year of existence, and the dam structure would have become so porous and weak that grouting cannot improve the quality of the deteriorated material remaining in the dam body. The 126 year old dam is not amenable to withstand the designed pressure through the process of pressure grouting and it makes the dam more unsafe rather than grouting. Moreover, the efficiency of grouting extends only up to a maximum of 5 to 8 years and it is only a temporary strengthening measure", it is advanced.
    It is stated that it is imperative that a century old dam should have all necessary instruments for monitoring deformation, seepage/leakage quantity and quality, uplift pressure, pore water pressure, temperature, reservoir level and seismicity, as per the guidelines of Central Water Commission viz. Guidelines for the instrumentation of Large Dams (2018)- "There is no comprehensive instrumentation plan including seismic instrumentation for Mullaperiyar dam which is essential for monitoring the safety of large dam which is 126-year-old dam and the relevant instruments embedded in the dam to monitor various parameters mentioned in the CWC guide lines for instrumentation of large dams, are not working."
    It is stated that Mullaikodi rain gauge station has been constructed by the state of Tamil Nadu, which is not a part of the land covered by the lease Deed of 1886; and in any case the State of Kerala has not barred access to the said rain gauge station but only regulated by insisting on plying through the boat maintained by the Forest Department of Kerala.
    It is submitted that, though the Empowered Committee concluded that the Mullaperiyar will remain safe, the Committee had also pointed out that, ".....a possibility cannot be ruled out that at some point of time in future, in spite of requisite upkeep of the Dam, it may suffer some distress due to reasons beyond anybody's control. The Committee recommended that in that case, the dam may need restoration/ strengthening measures which may take years for implementation. It also might need temporary evacuation of the reservoir level to facilitate implementation of restoration"- "The Empowered Committee also suggested two alternatives as 'Way Forward - Towards An Amicable Resolution' of the issue for the consideration of the Court wherein the construction of new dam and providing low level outlets of adequate capacity to lower the reservoir water level to a specified elevation was suggested as two alternatives and this Hon'ble Court in its judgment has endorsed the same in the judgment dated 07.05.2014 in OS 3 of 2006. It is further stated that the spatial and temporal variability in rainfall, recent incidents of heavy erratic rainfall over Kerala specifically in the Mullaperiyar catchment over the last four years, consequent sudden rise in the reservoir water level, projected change in rainfall patterns due to climate change and its impact on floods, the age of the Mullaperiyar dam and its safety, has caused concerns on the safety of the structure and lives of lakhs of people residing downstream of dam."
    The state of Kerala has denied that the said status report of the CWC states that Kerala is obstructing maintenance works or strengthening measures as alleged or at all- "It is an admitted position that the Supervisory Committee during its routine yearly inspections of Mullaperiyar dam is only conducting visual inspection and no detailed inspection as per CWC guidelines are being done. It is stated that the existing Mullaperiyar dam is one of the oldest gravity dams of its kind and nature currently existing in the world. The dam is not provided with a comprehensive instrumentation plan including seismic instrumentation. Though the state of Kerala has been persistently requesting for a comprehensive instrumentation plan, the same has not been installed. The seismic accelerographs as recommended by the DSARP Panel has not been installed even after three decades. The seepage noticed in the dam is not the actual seepage of the dam as the seepage measuring devices are not installed in the old main dam. Hence any disaster will be a threat to the lives and property of people in the downstream of dam. It is therefore not admitted that, it is not justifiable to have a fresh review before carrying out the strengthening measures ordered by this Hon'ble Court."
    It is denied by Kerala that the various parameters of the dam are within acceptable limits or that there is no necessity to have a fresh review on the safety of the dam for storing water +142ft, as alleged or at all. It is submitted that the statement that Mullaperiyar dam is behaving well in all respects is devoid of merits.
    It is stated that the Central Water Commission in their Guidelines for their safety inspection of the dams in 2018 as well as National Committee on Dam Safety has prescribed Comprehensive dam safety evaluations for all dams at regular intervals to ensure their safety irrespective of whether rehabilitation works have been carried out in the dam or not. Further, after the dam safety evaluation by independent experts, necessary rehabilitation works if any required will be suggested, which needs to be implemented.
    "The Mullaperiyar dam and the catchment area received two major floods after the pronouncement of the judgment (2014) and the catchment received erratic heavy rainfall in recent years. Also, many tremors/earthquakes have been reported near the dam site during the last years. All the above phenomena have caused impact on the safety of the structure", it is emphasised.

    Case Title: Dr. Joe Joseph v. State Of Tamil Nadu


    Next Story