Possession Of Plot Offered Twice, HUDA Not Liable For Delay Caused Due To Road Shifting, Subsequent Plan Approval: NCDRC

Smita Singh

12 April 2025 4:00 PM IST

  • Possession Of Plot Offered Twice, HUDA Not Liable For Delay Caused Due To Road Shifting, Subsequent Plan Approval: NCDRC

    The National Consumer Disputes Redressal Commission, New Delhi bench of Justice AP Sahi (President) and Bharatkumar Pandya (Member) held that the Haryana Urban Development Authority (HUDA) was not liable for delay in delivering possession of an allotted plot, as it had offered the same twice, and the initial delay was caused due to shifting of a road and approval of a revised...