Interim Relief Under The A&C Act Obtained Without Disclosing Material Evidence, Calcutta High Court Imposes Cost Of Rs. 50 Thousand On Each Petitioner

ausaf ayyub

3 July 2023 11:00 AM IST

  • Interim Relief Under The A&C Act Obtained Without Disclosing Material Evidence, Calcutta High Court Imposes Cost Of Rs. 50 Thousand On Each Petitioner

    The High Court of Calcutta has held that a party approaching the Court for relief must do so with clean hands and is under an obligation to disclose all material facts that have bearing on the adjudication of the issues in the case.The bench of Justice Shekhar B. Saraf held that the doors of justice would be closed for litigants approaching the court with a case built on falsehood,...

    The High Court of Calcutta has held that a party approaching the Court for relief must do so with clean hands and is under an obligation to disclose all material facts that have bearing on the adjudication of the issues in the case.

    The bench of Justice Shekhar B. Saraf held that the doors of justice would be closed for litigants approaching the court with a case built on falsehood, fraudulent concealment or suppression of material facts.

    The Court recalled its earlier order wherein it had granted interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 to a party that concealed material facts of the dispute from the Court at the time of seeking such relief. The Court imposed cost of Rs. 50 thousand on each of the petitioners.

    Facts

    The petitioner no. 1 is an LLP Firm. The petitioner nos. 2-5, respondent nos. 3 & 6 were purported partners in the firm. Respondent No. 4 & 5 were the founding partners. Respondent nos. 1 & 2/applicant were also partners in the firm.

    In the year August 2021, the respondent nos. 4 & 5 approached the petitioners to offer them the partnership in the firm and transfer the firm to them on receipt of capital contributions and settlement of dues to the erstwhile creditors of the firm. Accordingly, supplementary agreements were prepared to include the petitioners as incoming partners and for retirement of the respondent nos. 4 & 5. However, as the petitioner failed to make any arrangement for capital infusion and discharge of existing debts of the company, the documents could not be executed and the originals of the agreements was retained by the respondent nos. 4-5. Accordingly, the respondent nos. 4-5 issued a letter of cancellation dated 28.10.2022 to the petitioners.

    Thereafter, the respondent no. 4-5 approached the applicants and offered to them their stakes in the partnership firm. Accordingly, the parties executed supplementary agreements dated 12.03.2022 and 14.03.2022 by way of which the applicants were inducted as partners and respondent nos. 4-5 retired from the partnership.

    However, in June 2022, the petitioners allegedly entered the office of the father of the applicants and took away the original undated and non-executed supplementary agreement that were made between the petitioners and respondent nos. 4-5. When they filed these documents with the Registrar of Companies (RoC), they were informed that the partnership already stood transferred in favour of applicants. Accordingly, they approached the Court under Section 9 of the A&C Act for interim reliefs. The Court allowed the petition under Section 9 and directed the applicants to maintain status quo in respect of the assets of the firm.

    Aggrieved by the order, the applicants filed an interlocutory application against the impugned order and prayed for vacation or recalling of the impugned order with costs.

    Contention of the Applicant

    The applicant made the following submissions in favour of the application:

    • The petitioner nos. 2-5 have obtained the interim relief by suppressing material facts from the court.
    • The petitioners are not the partners in the firm as the agreements regarding their inclusion could not be executed due to their failure to make arrangements for the infusion of funds and discharge of debts of the firm which led the respondent nos. 4-5 to approach the applicants for the same purpose. Moreover, the petitioners have not informed the court regarding the cancellation letter dated 28.10.2022 issued by the respondents to the petitioners.
    • The petitioners fraudulently executed the supplementary agreements after forcefully obtaining them from the office of the father of the applicant. The stamp paper on which these supplementary agreements were drawn dates back to 21.08.2021, however, they were executed only in the June 2022 which shows the fraud committed on behalf of the petitioners.
    • The applicants were duly made the partners and the respondent nos. 4-5 retired from the firm vide agreements dated 12.03.2022 and 14.03.2022, therefore, any question of respondents executing any subsequent agreement with the petitioner does not arise as they were not the owner/partners of the firm.
    • The Court erred in passing the impugned order on the premise that the petitioners were the partners in the firm, therefore, it must be recalled.

    Analysis by the Court

    The Court observed that upon a careful perusal of the supplementary agreements filed by the petitioners, it appears that the stamp paper on which these were drawn dates back to August 2021 while these were executed only in June 2022, therefore, the Court observed that it was “undeniably odd that crucial documents such as supplementary agreements modifying the partnership composition itself were executed on stamp papers which were bought more than nine months back from date.”

    The Court also took note of the fact that the respondents issued a letter of cancellation on 28.10.2021 regarding the cancellation of the undated signed agreement for want of receipt of consideration from the petitioners, therefore, any question of them being executed after their cancellation does not arise. Moreover, the petitioners failed to give any proof if they had actually discharged their obligation of infusion of capital in consideration of their induction into the partnership firm which is required in terms of clause 2 of these agreements and also by Section 33 of LLP Act, 2008. All these facts land credence to the claim of the applicants regarding the fraudulent execution of the supplementary agreements by the petitioners.

    The Court also observed that the claim of execution of supplementary in favour of the applicants is also backed by the fact that Form 9 (consent to act as designated partner) to the petitioner firm on March 11, 2023. Similarly, Form 13 (notice of cessation by erstwhile designated partner to the other designated partner) was issued to the other designated partners on March 12, 2022 and March 14, 2022 by respondent nos. 5 and 4 respectively. Moreover, the other required forms were duly filed by the applicants with the RoC.

    The Court also observed that pursuant to the execution of supplementary agreements in favour of the applicants, the respondent nos. 4-5 also handed over all the documents, including, the un-executed supplementary agreements with the petitioners, to the applicants. Therefore, the argument of the applicants regarding forceful obtaining of undated supplementary agreements appears to be well founded. Also, the applicants have furnished proofs of their investment in the company including capital contribution and arrangement of funds for financial assistance in terms of the agreement.

    The Court held that the dates were minted on the supplementary agreements at a later stage and therefore, the said agreements annexed by the petitioners are forged. By concealing the cancellation letter dated 28.10.2021, the petitioners have suppressed the materials facts in obtaining the impugned interim order. The Court held that the petitioners engaged in the abuse of process of Court by forging documents to claim the relief.

    The Court held a party approaching the Court for relief must do so with clean hands and is under an obligation to disclose all material facts that have bearing on the adjudication of the issues in the case. It held that the doors of justice would be closed for litigants approaching the court with a case built on falsehood, fraudulent concealment or suppression of material facts.

    Accordingly, the Court allowed the application and recalled its earlier order. Further, it imposed cost of Rs. 50 thousand on each petitioner.

    Case Details: Omkar Tradecomm LLP v. Mayank Agarwal, IA No. GA 1 of 2023 in AP 851 of 2022

    Date: 15.06.2023

    Counsel for the Applicants: Mr. Krishnaraj Thaker, Adv. Ms. Suchismita Ghosh Chatterjee, Adv. Mr. Shivam Bhimsaria, Adv. Mr. Tanay Agarwal, Adv. Mr. Nayantara Bhattacharya, Adv

    Counsel for the Petitioners: Mr. Dhruba Ghosh, Sr. Adv. Mr. Pranit Bag, Adv. Mr. Rahul Poddar, Adv. Ms. Oindrila Ghosal, Adv. Ms. Shrayasi Dhang, Adv.

    Click Here To Read/Download Judgment

    Next Story