REAL ESTATE WEEKLY ROUND UP:[16 th DECEMBER – 22 nd DECEMBER 2024]

Update: 2024-12-25 07:52 GMT
Click the Play button to listen to article
story

Haryana Real Estate Regulatory Authority Delay Of More Than 2.7 Years In Completing Construction Of Project, Haryana RERA Orders Raheja Developers To Refund Rs. 27.98 Lakhs To Homebuyer Case – Arun Shrivastava Versus M/S Raheja Developers Limited Citation – Complaint no 4974 of 2023 Haryana Real Estate Regulatory Authority (Authority) bench, comprising Ashok Sangwan...

Your free access to Live Law has expired
Please Subscribe for unlimited access to Live Law Archives, Weekly/Monthly Digest, Exclusive Notifications, Comments, Ad Free Version, Petition Copies, Judgement/Order Copies.

Haryana Real Estate Regulatory Authority

Delay Of More Than 2.7 Years In Completing Construction Of Project, Haryana RERA Orders Raheja Developers To Refund Rs. 27.98 Lakhs To Homebuyer

Case – Arun Shrivastava Versus M/S Raheja Developers Limited

Citation – Complaint no 4974 of 2023

Haryana Real Estate Regulatory Authority (Authority) bench, comprising Ashok Sangwan (Member), has directed M/S Raheja Developers Limited to refund ₹27.98 Lakhs with interest to homebuyer who purchased a flat in their Raheja Maheshwara Project.

Inordinate Delay Of More Than 10 Years, Haryana RERA Directs Ansal Builders To Refund 1.07 Crores To Homebuyer

Case – Sheela Srivastava & others Versus M/s Ansal Housing & Construction Ltd.

Citation – Complaint no: 805 of 2023

Haryana Real Estate Regulatory Authority (Authority) bench comprising Ashok Sangwan (Member) has directed M/s Ansal Housing and Constructions Limited to refund Rs. 1.07 crores with 11.10% interest to the homebuyer after facing an inordinate delay of more than 10 years in receiving possession of the flat.

Initially, the homebuyer was allotted a flat in 2013. Due to delays the homebuyer's booking was transferred to another project twice, making it a total of three times. According to the final Floor Buyer's Agreement the builder was supposed to hand over possession of the flat by 21st July 2022.

Haryana RERA - No Additional Compensation To Homebuyer When Interest For Delayed Possession Already Granted

Case – Mr. Raghav Manocha & Abhinav Manocha Versus M/s. Emaar MGF Land Limited

Citation – Complaint No: 13 of 2024

Haryana Real Estate Regulatory Authority (Authority) Bench comprising Rajender Kumar (Adjudicating Officer) dismissed the homebuyer's complaint against M/s. Emaar MGF Land Limited seeking additional compensation.

Authority held that no additional compensation can be granted to the homebuyer when delay possession compensation has already been granted along with interest under Section 18(1) of the RERA, 2016.

Maharashtra Real Estate Regulatory Authority

Maharashtra RERA Directs Godrej Skyline Developers To Refund Full Booking Amount Paid By Homebuyer With Interest

Case – Ashok Babaji Sable Versus Godrej Skyline Developers Pvt Ltd

Citation – Complaint No. CC005000000064485

Maharashtra Real Estate Regulatory Authority (Authority) bench comprising of Ravindra Deshpande (Member-II) directed Godrej Skyline Developers Pvt Ltd to fully refund the booking amount paid by the homebuyer with interest. The bench observed that the allotment letter contained coercive terms and that the booking amount did not fall under the definition of earnest money as per the application form.

Haryana Consumer Disputes Redressal Commission

Haryana State Commission Holds Ansal Properties Liable For Delay In Possession, Orders Refund And Compensation

Case title: Mrs. Neeru Bala Mahendru vs Ansal Properties & Infrastructure Limited & Ors.

Case No: Consumer Complaint No.481 of 2018

The State Consumer Disputes Redressal Commission, Haryana presided by Justice T.P.S Mann (President), Mr. S. P. Sood (Judicial Member) and Ms. Manjula (Member) held Ansal Properties & Infrastructure Limited liable for delay in possession of residential plot for several years. Further, the commission ordered refund and compensation for deficiency in service.

Ernakulam District Commission

Failure To Complete Construction On Time, Ernakulam District Commission Holds Builder Liable

Case Title: Karuppuswami Vs. Thodiyil Builders

Case Number: C.C. No. 111/2024

The Ernakulam District Commission, presided by Shri. D.B. Binu, Shri. V. Ramachandran and Smt. Sreevidhia T.N., in a complaint against Thodiyil Builders held that delays in handing over the possession and evidence of substandard work amounts to deficiency in service.

Telangana Real Estate Regulatory Authority

Telangana RERA Permits Association Of Homebuyers To Take Over Project Due To Builder's Failure

Case – Abhishek Singh Versus M/s Jayathri Infrastructures India Pvt Ltd.– “Jaya Platinum Project” Along with 12 Others

Citation - Complaint No.1269 of 2023 Along with 12 Others

While invoking Section 8 of the Real Estate (Regulation and Development) Act, 2016, the Telangana Real Estate Regulatory Authority (Authority) bench comprising Justice Dr. N. Satyanarayana (Chairperson), K. Srinivasa Rao (Member), and Laxmi Narayana Jannu (Member) permitted the Association of Homebuyers (allottees) to take over the project and complete it within eight months.

Section 8 allows the Authority to take necessary actions if a project's registration lapses or is revoked.

Delhi District Commission

District Commission Misapplied Supreme Court's Ruling: Chandigarh State Commission Remands Sahara Prime City Case For Fresh Adjudication

Case title: Smt. Neelima Joshi vs. Sahara Group & Ors.

Case No: Appeal No. 198 of 2024

The State Consumer Disputes Redressal Commission, Chandigarh presided by Justice Raj Shekhar Attri (President) and Mr. Rajesh K. Arya (Member) held that the District Commission has misapplied the decision of Supreme Court in Pinak Pani Mohanty vs Union of India as Sahara Prime City Ltd. was not party to that case.

The State Commission remanded the case to the District Commission for fresh adjudication.

Failure To Hand Over Commercial Space To Purchasers Is 'Deficiency In Service': Delhi State Commission

Case name: Jai Narayan vs Parsvnath developers pvt. Ltd

Case number: Complaint Case No. 984/2019

The Delhi State Commission has held that default in delivering the commercial space by Parsvnath developers booked by the complainants is 'deficiency in service'. The bench presided by Member Bimla Kumari observed that purchasers cannot be made to wait for an indefinite period of time and thus granted adequate compensation.

Karnataka Real Estate Regulatory Authority

Karnataka RERA Orders Dharwad-Based Builder To Refund ₹38.8 Lakhs To Homebuyer Due To Delay

Case – Shreepad G Shindgikar and Rahul Shindgikar Versus Skytown Builders and Developers

Citation – Complaint No: CMP/211005/0008417

Karnataka Real Estate Regulatory Authority (Authority) bench comprising Neelmani N. Raju (Member) has directed the Dharwad-based builder named Skytown Builders and Developers to refund ₹38.8 lakhs to the homebuyer after the builder failed to provide possession of the flat on time.
Karnataka RERA Holds Shrivision Homes Liable For Delayed Possession, Orders 30.2 Lakhs Interest To Homebuyer

Case – Santosh Kumar Sahu & others Versus M/S Shrivision Homes Pvt. Ltd

Citation – Complaint No: 00357/ 2024

Karnataka Real Estate Regulatory Authority (Authority) bench, comprising GR Reddy (Member), has directed M/S Shrivision Homes Pvt. Ltd to pay Rs. 30.2 Lakhs to the homebuyer as interest for delay in handing over possession of the flat.

West Bengal Real Estate Appellate Tribunal

WBREAT Upholds Order Directing Builder To Pay Over ₹56 Lakh Over Failure To Provide Possession Of Four Plots By November 2016

Case Title – M/s Janapriyo Real Estate Pvt. Ltd. Versus Arindam Mitra

Citation – WBREAT/APPEAL NO. — 06/2023

West Bengal Real Estate Appellate Tribunal (Tribunal) bench comprising Justice Rabindranath Samanta (Chairperson), Gour Sunder Banerjee (Judicial Member) and Dr. Subrat Mukherjee (Administration Member) has provided relief to the complainant who purchased four plots by paying advance money in the builder's mini township project and was expecting possession by November 2016.

The Tribunal upheld the Authority's order directing the builder to refund the principal amount of Rs. 44,08,600/- paid by the complainant to purchase the plots, along with Rs. 12,04,849/- as interest.

Telangana State Commission

Telangana State Commission Validates Builder's Claim of Outstanding Payments

Case Title: M/s Narne Estates Pvt., Ltd. Vs. Shri Mohd. Adbul Rahim

Case Number: F.A. No. 381/2020

The Telangana State Commission, presided by Sri. V. V. Seshubabu and K. Ranga Rao allowed an appeal by Narne Estates and modified the District Commission's order. The Commission acknowledged the builder's claim of outstanding payments on behalf of the buyer and directed the buyer to clear the same.