HARYANA REAL ESTATE REGULATORY AUTHORITY Haryana RERA Orders Raheja Developers To Refund Three Homebuyers Of Raheja Revanta Project Case – Arvinder Singh Aneia and Preeti Aneja Versus Raheja Developers Limited Along with 2 others Citation – Complaint No. 2205/2023 and 2 others Haryana Real Estate Regulatory Authority (Authority) bench comprising Ashok Sangwan (Member)...

Your free access to Live Law has expired
Please Subscribe for unlimited access to Live Law Archives, Weekly/Monthly Digest, Exclusive Notifications, Comments, Ad Free Version, Petition Copies, Judgement/Order Copies.

HARYANA REAL ESTATE REGULATORY AUTHORITY

Haryana RERA Orders Raheja Developers To Refund Three Homebuyers Of Raheja Revanta Project

Case – Arvinder Singh Aneia and Preeti Aneja Versus Raheja Developers Limited Along with 2 others

Citation – Complaint No. 2205/2023 and 2 others

Haryana Real Estate Regulatory Authority (Authority) bench comprising Ashok Sangwan (Member) has directed Raheja Developers to refund three homebuyers who purchased their flats in the Raheja Revanta Project in 2012 with interest. The homebuyers decided to withdraw from the project after the builder failed to hand over possession even after a delay of 7 years.

TELANGANA REAL ESTATE REGULATORY AUTHORITY

Telangana RERA Imposes Penalty Of Rs. 17.88 Lakhs On Sterling Homes For Delays & Deviations From Sanctioned Plan

Case – Allam Nagaraju & 14 others Versus M/s Sterling Homes Private Ltd

Citation - COMPLAINT NO.45 OF 2024

While hearing the complaints of 15 homebuyers, Telangana Real Estate Regulatory Authority (Authority) bench comprising Justice Dr. N. Satyanarayana (Chairperson), K. Srinivasa Rao (Member) and Laxmi Narayana Jannu (Member) imposed a penalty of ₹17.88 lakhs on M/s Sterling Homes Private Ltd for delays and deviations from the original sanctioned plan.

The builder merged the clubhouse facility which was originally meant for the homebuyers of Phase I of the project with the upcoming Phase II.

WEST BENGAL REAL ESTATE APPELLATE TRIBUNAL

WB REAT Facilitates Settlement Between Builder And Homebuyer Over Termination Of Flat Booking Due To Non-Payment Of Total Consideration

Case – Smt. Seema Pandey Versus M/s P.S. Group Realty Pvt. Ltd.

Citation – WBREAT / APPEAL No. - 009/2024

West Bengal Real Estate Appellate Tribunal (Tribunal) bench, comprising Justice Rabindranath Samanta (Chairperson) and Dr. Subrat Mukherjee (Administration Member), oversaw and facilitated a settlement between a builder and a homebuyer.

The homebuyer had purchased a flat in the builder's project, but his booking was terminated by the builder after he failed to pay the remaining amount on time.

KARNATAKA REAL ESTATE REGULATORY AUTHORITY

Karnataka RERA Directs Ozone Urbana Infra Developers To Refund Rs. 1.08 Crores To Homebuyer For Delay

Case – A Hanumantha Char Versus Ozone Urbana Infra Developers Private Ltd

Citation – Complaint No: 00173/2024

Karnataka Real Estate Regulatory Authority (Authority) bench, comprising Neelmani N Raju (Member) has directed Ozone Urbana Infra Developers to refund Rs. 1.08 crores to the homebuyer after the builder failed to provide possession of the flat on time.

The homebuyer purchased a flat in the builder's Bengaluru Rural project to enjoy his retirement in a pollution-free green belt, away from the city. He was expecting possession of his flat by June 2023.

MAHARASHTRA REAL ESTATE REGULATORY AUTHORITY

Maharashtra RERA Directs Pune Housing And Area Development Board To Rectify Structural Defects In The Project

Case – Sharad Agrawal Versus Pune House & Area Development Board, MHADA

Citation – Complaint No. CC005000000106546

Maharashtra Real Estate Regulatory Authority (Authority) bench comprising Mahesh Pathak (Member) has directed the Pune Housing and Area Development Board (PHADB) to rectify the structural defects in the project within 30 days.